Scope of Work: 

The work comprised reroofing of existing asphalt, single ply and metal roofs with new Garland high performance elastomeric felt weatherproofing system and thermal insulation.

 

Existing roofs were carefully stripped and or prepared to receive new system.  Outlets and guttering were removed and new rainwater outlets, downpipes and lead chutes were installed.

 

Rooflights were replaced along with redundant openings being sealed over including making good to internal linings.

 

New PVC boards were installed to replace damaged and decayed timber cladding.

 

The works also included internal making good, decorations and external decorations.

 

Project Overview: 

Principal Contractor: Malone Roofing
Client: Arnewood School
Contract Administrator: Kendall Kingscott
Site: New Milton 
Value: Circa £400k