Scope of Work: 

Erect safety netting to steel structure and install galvanised steel metal decking and gutters. Install top hats, clips, quilt insulation and colour coated finished Kalzip 65/400 roof sheets including all associated gutters, trims, flashings, ridge pieces etc.

Kalzip rainscreen cladding.

Install Sarnafil PVC single ply membrane gutters and roof top structures.

Latchways mansafe systems.

PPC eaves, fascia and soffit system installed to galvanised steel support work. PPC aluminium cappings fixed to plywood sub base on parapet walls.

Radmat Permaquick hot melt roof system to terrace areas including extruded polystyrene insulation and concrete paving slabs on supports.

Project Overview: 

Main Contractor: HG Construction
Client: Workspace Group PLC
Site:  Westminster Business Square
Value: Circa £300k